Collegiate Sports Paging System Requirements Management Plan Version 1.0
Revision History
Table of Contents
1.3Definitions, Acronyms, and Abbreviations 2.1Organization, Responsibilities, and Interfaces 2.2Tools, Environment, and Infrastructure 3.The Requirements Management Program 3.1Requirements Identification 3.5Requirements Change Management
Requirements Management Plan 1. Introduction1.1 PurposeThis document
describes the guidelines used by the Collegiate Sports Paging System (CSPS)
project for establishing the requirements documents, requirement types,
requirements attributes, and tracability in order to manage their software
project requirements. It will also serve as the configuration document
for the Rational RequisiteProâ
requirements management tool.
1.2 ScopeThis plan pertains to all phases of the
project.
1.3 Definitions, Acronyms, and AbbreviationsSee Glossary
1.4 ReferencesCSPS Software
Development Plan
CSPS Development
Case
CSPS Measurement Plan CSPS Configuration Management Plan 2. Requirements Management2.1 Organization, Responsibilities, and InterfacesSee the CSPS Software Development Plan.
2.2 Tools, Environment, and InfrastructureRational
RequisitePro will be used
to manage requirements. For other information about the infrastructure
and environment, refer to the CSPS Software Development Plan.
3. The Requirements Management Program3.1 Requirements Identification
3.2 TraceabilityFigure -1 - Traceability diagram Criteria for FEATFeatures will
be traced to use cases.
Criteria for NEEDUser needs
will be traced to features(FEAT). Any needs not traced to a FEAT
will not be implemented.
Criteria for UCUse-cases
will be traced to test cases.
Criteria for SUPPSupplemental
specifications will be traced to test cases.
3.3 AttributesAttributes for FEATStatus
Set after negotiation and review by the
project management team. Tracks progress during definition of the project
baseline.
Benefit Set by Marketing, the product manager or
the business analyst. All requirements are not created equal. Ranking requirements
by their relative benefit to the end user opens a dialogue with customers,
analysts and members of the development team. Used in managing scope and
determining development priority.
Effort Set by the development team. Because some features require more time and resources than others, estimating the number of team or person-weeks, lines of code required or function points, for example, is the best way to gauge complexity and set expectations of what can and cannot be accomplished in a given time frame. Used in managing scope and determining development priority. Risk Set by development team based on the probability the project will experience undesirable events, such as cost overruns, schedule delays or even cancellation. Most project managers find categorizing risks as high, medium, and low sufficient, although finer gradations are possible. Risk can often be assessed indirectly by measuring the uncertainty (range) of the projects teams schedule estimate. Stability Set by analyst and development team based on the probability the feature will change or the team’s understanding of the feature will change. Used to help establish development priorities and determine those items for which additional elicitation is the appropriate next action. Target Release Records the intended product version in which the feature will first appear. This field can be used to allocate features from a Vision document into a particular baseline release. When combined with the status field, your team can propose, record and discuss various features of the release without committing them to development. Only features whose Status is set to Incorporated and whose Target Release is defined will be implemented. When scope management occurs, the Target Release Version Number can be increased so the item will remain in the Vision document but will be scheduled for a later release. Assigned To In many projects, features will be assigned to "feature teams" responsible for further elicitation, writing the software requirements and implementation. This simple pull down list will help everyone on the project team better understand responsibilities. Reason This text field is used to track the source of the requested feature. Requirements exist for specific reasons. This field records an explanation or a reference to an explanation. For example, the reference might be to a page and line number of a product requirement specification, or to a minute marker on a video of an important customer interview. Attributes for NEEDStatus
Set after negotiation and review by the
project management team. Tracks progress during definition of the project
baseline.
Effort Set by the development team. Because some needs require more time and resources than others, estimating the number of team or person-weeks, lines of code required or function points, for example, is the best way to gauge complexity and set expectations of what can and cannot be accomplished in a given time frame. Used in managing scope and determining development priority. Risk Set by development team based on the probability the project will experience undesirable events, such as cost overruns, schedule delays or even cancellation. Most project managers find categorizing risks as high, medium, and low sufficient, although finer gradations are possible. Risk can often be assessed indirectly by measuring the uncertainty (range) of the projects teams schedule estimate. Stability Set by analyst and development team based on the probability the need will change or the team’s understanding of the need will change. Used to help establish development priorities and determine those items for which additional elicitation is the appropriate next action. Target Release Records the intended product version in which the need will first be met. This field can be used to allocate features from a Vision document into a particular baseline release. When combined with the status field, your team can propose, record and discuss various features of the release without committing them to development. Only needs whose Status is set to Incorporated and whose Target Release is defined will be met. When scope management occurs, the Target Release Version Number can be increased so the item will remain in the Vision document but will be scheduled for a later release. Reason This text field is used to track the source of the need. Requirements exist for specific reasons. This field records an explanation or a reference to an explanation. For example, the reference might be to a page and line number of a product requirement specification, or to a minute marker on a video of an important customer interview. Attributes for UCSet after negotiation and review by the
project management team. Tracks progress during definition of the project
baseline.
Benefit Set by Marketing, the product manager or
the business analyst. All requirements are not created equal. Ranking use-cases
by their relative benefit to the end user opens a dialogue with customers,
analysts and members of the development team. Used in managing scope and
determining development priority.
Effort Set by the development team. Because some use-cases require more time and resources than others, estimating the number of team or person-weeks, lines of code required or function points, for example, is the best way to gauge complexity and set expectations of what can and cannot be accomplished in a given time frame. Used in managing scope and determining development priority. Risk Set by development team based on the probability the project will experience undesirable events, such as cost overruns, schedule delays or even cancellation. Most project managers find categorizing risks as high, medium, and low sufficient, although finer gradations are possible. Risk can often be assessed indirectly by measuring the uncertainty (range) of the projects teams schedule estimate. Stability Set by analyst and development team based on the probability the use-case will change or the team’s understanding of the use-case will change. Used to help establish development priorities and determine those items for which additional elicitation is the appropriate next action. Target Release Records the intended product version in which the use-case will first appear. This field can be used to allocate use-cases from a Use Case Survey document into a particular baseline release. When combined with the status field, your team can propose, record and discuss various use-cases of the release without committing them to development. Only use-cases whose Status is set to Incorporated and whose Target Release is defined will be implemented. When scope management occurs, the Target Release Version Number can be increased so the item will remain in the Vision document but will be scheduled for a later release. Assigned To In many projects, use-cases will be assigned to teams responsible for further elicitation, writing the software requirements and implementation. This simple pull down list will help everyone on the project team better understand responsibilities. Reason This text field is used to track the source of the requested use-case. Requirements exist for specific reasons. This field records an explanation or a reference to an explanation. For example, the reference might be to a page and line number of a product requirement specification, or to a minute marker on a video of an important customer interview. Attributes for SUPPStatus
Set after negotiation and review by the
project management team. Tracks progress during definition of the project
baseline.
Benefit Set by Marketing, the product manager or
the business analyst. All requirements are not created equal. Ranking requirements
by their relative benefit to the end user opens a dialogue with customers,
analysts and members of the development team. Used in managing scope and
determining development priority.
Effort Set by the development team. Because some specifications require more time and resources than others, estimating the number of team or person-weeks, lines of code required or function points, for example, is the best way to gauge complexity and set expectations of what can and cannot be accomplished in a given time frame. Used in managing scope and determining development priority. Risk Set by development team based on the probability the project will experience undesirable events, such as cost overruns, schedule delays or even cancellation. Most project managers find categorizing risks as high, medium, and low sufficient, although finer gradations are possible. Risk can often be assessed indirectly by measuring the uncertainty (range) of the projects teams schedule estimate. Stability Set by analyst and development team based on the probability the specification will change or the team’s understanding of the specification will change. Used to help establish development priorities and determine those items for which additional elicitation is the appropriate next action. Target Release Records the intended product version in which the specified attribute or feature will first appear. This field can be used to allocate specifications into a particular baseline release. When combined with the status field, your team can propose, record and discuss various specifications of the release without committing them to development. Only specifications whose Status is set to Incorporated and whose Target Release is defined will be implemented. When scope management occurs, the Target Release Version Number can be increased so the item will remain in the supplemental specification document but will be scheduled for a later release. Assigned To In many projects, specified attributes or features will be assigned to teams responsible for further elicitation, writing the software requirements and implementation. This simple pull down list will help everyone on the project team better understand responsibilities. 3.4 Reports and MeasuresSee the CSPS Measurement Plan.
3.5 Requirements Change ManagementSee the CSPS Configuration Management Plan.
The following access groups will be set
up to control access to requirements in Rational RequisitePro.
·Tool Administrator – has full access to every part of the tool. Can add and remove people, change their access rights, etc. ·Author – can create new requirements ·Project Manager – sets the status of requirements ·Tester_QA – sets the status of test case requirements. 3.6 Workflows and ActivitiesSee the CSPS Development Case.
4. MilestonesSee the CSPS Software Development Plan.
5. Training and ResourcesSee the CSPS Software Development Plan.
|
|
|