Roles and Activities > Developer Role Set > Integrator > Promote Baselines
Activity:
|
Purpose
|
|
Steps | |
Input
Artifacts:
|
Resulting
Artifacts:
|
Frequency: On-going as part of the Iterative Development Process | |
Role: Integrator | |
Tool Mentor: |
Workflow Details: |
Baselines help to keep the project team synchronized. They provide a view to the most current version of the project assets. As such, baselines need to created on a regular basis in accordance with the project's CM policies.
Baselines could be named after the phase and iteration in which they area created. In this instance the name of a baseline could be BL-Product-X-c2, implying that it is the baseline created at the end of the second iteration in the Construction Phase.
However, the other labeling conventions for baselines could be commensurate with the level of testing, and quality, a product baseline may have achieved. In this case, the baseline could, for example, be tagged as:
- Integration Tested,
- System Tested,
- Acceptance Tested, and
- Production.
The labeling convention described above suggests that the once a baseline has been tested, and verified, to have achieved a certain quality level it is promoted and tagged with higher order label.
Rational Unified Process |