Artifacts > Project Management Artifact Set > Risk List


Risk List
A sorted list of known and open risks to the project, sorted in decreasing order of importance and associated with specific mitigation or contingency actions.
Role:

Project Manager

Enclosed in: Risk Management Plan of the Software Development Plan.
Templates:
Examples:
More information:

Input to Activities: Output from Activities:

Purpose To top of page

The Risk List is designed to capture the perceived risks to the success of the project. It identifies, in decreasing order of priority, the events that could lead to a significant negative outcome. It serves as a focal point for project activities and is the basis around which iterations are organized.

Timing To top of page

The Risk List is maintained throughout the project. It is created early in the Inception phase, and is continually updated as new risks are uncovered and existing risks are mitigated or retired. At a minimum, it is revisited at the end of each iteration, as the iteration is assessed.

Responsibility To top of page

The Project Manager is responsible for maintaining the Risk List and keeping it updated.

Tailoring To top of page

The Risk List should capture the critical and serious risks—if you find this list extending beyond 20, carefully consider whether they are really serious risks. Tracking more than 20 risks is an onerous task.



Copyright  © 1987 - 2001 Rational Software Corporation


Display Rational Unified Process using frames

Rational Unified Process