This Iteration Plan describes the detailed plans for the Transition Iteration
of the Project. During this iteration, the WebNewsOnLine staff will be prepared
to maintain the Collegiate Sports Paging System.
The Transition Iteration Plan applies to the Collegiate Sports Paging System
project being developed by Context Integration for WebNewsOnLine . This document
will be used by the Project Manager and by the project team.
The Transition Iteration prepares the WebNewsOnLine staff to support and
maintain the system going forward.
The following table illustrates the tasks with their planned start and end
dates.
Task |
Start |
End |
Hold Transition Kick-off Meeting |
Mon 2/14/00 |
Tue 2/15/00 |
Production Preparation |
Tue 2/15/00 |
Wed 2/16/00 |
Release Procedures |
Tue 2/15/00 |
Tue 2/15/00 |
"Release checklist created, reviewed, and
baselined" |
Tue 2/15/00 |
Tue 2/15/00 |
Release approval signed by all parties and put
under change control |
Tue 2/15/00 |
Tue 2/15/00 |
Operations Procedures |
Tue 2/15/00 |
Wed 2/16/00 |
"Detailed Contingency and Disaster
Recovery Plan created, reviewed, and baselined" |
Tue 2/15/00 |
Tue 2/15/00 |
Complete Operations Training materials |
Tue 2/15/00 |
Tue 2/15/00 |
Train Operations Team |
Tue 2/15/00 |
Wed 2/16/00 |
Obtain Sign-off |
Wed 2/16/00 |
Wed 2/16/00 |
Release & Operations Procedures Completed |
Wed 2/16/00 |
Wed 2/16/00 |
Production Environment |
Wed 2/16/00 |
Wed 2/16/00 |
"Production hardware acquired, installed
and configured" |
Wed 2/16/00 |
Wed 2/16/00 |
Network configuration completed |
Wed 2/16/00 |
Wed 2/16/00 |
Production data loaded |
Wed 2/16/00 |
Wed 2/16/00 |
Integration with legacy/external systems
completed |
Wed 2/16/00 |
Wed 2/16/00 |
Full system testing |
Wed 2/16/00 |
Mon 2/21/00 |
Conduct Functionality testing |
Wed 2/16/00 |
Wed 2/16/00 |
Conduct Performance testing |
Wed 2/16/00 |
Thu 2/17/00 |
Conduct Load Testing |
Thu 2/17/00 |
Fri 2/18/00 |
"Modify System for Functionality, or
Performance as necessary" |
Fri 2/18/00 |
Mon 2/21/00 |
"Conduct Regression Testing for
Functionality, Performance & Load " |
Mon 2/21/00 |
Mon 2/21/00 |
Full System Testing Completed |
Mon 2/21/00 |
Mon 2/21/00 |
Final Acceptance Testing |
Mon 2/21/00 |
Tue 2/22/00 |
Perform User Acceptance Test (1) |
Mon 2/21/00 |
Mon 2/21/00 |
Performance Tuning |
Mon 2/21/00 |
Tue 2/22/00 |
Perform User Acceptance Test (2) |
Tue 2/22/00 |
Tue 2/22/00 |
User Acceptance Testing Complete |
Tue 2/22/00 |
Tue 2/22/00 |
Business User Training |
Tue 2/22/00 |
Wed 2/23/00 |
User training materials completed |
Tue 2/22/00 |
Wed 2/23/00 |
"User Training environment (training data,
etc.) created" |
Wed 2/23/00 |
Wed 2/23/00 |
Business User Training Complete |
Wed 2/23/00 |
Wed 2/23/00 |
Transition Wrap-up |
Wed 2/23/00 |
Wed 2/23/00 |
Conduct Quality Check Meeting with Client |
Wed 2/23/00 |
Wed 2/23/00 |
Review Transition Wrap-up Checklist for
Completion |
Wed 2/23/00 |
Wed 2/23/00 |
"Have team, including client project
manager, complete the work release sign-off form" |
Wed 2/23/00 |
Wed 2/23/00 |
Move appropriate deliverables from Project
Homepage to IAN Artifacts |
Wed 2/23/00 |
Wed 2/23/00 |
Transition Complete - System in production |
Wed 2/23/00 |
Wed 2/23/00 |
The following deliverables or artifacts will be generated and reviewed during
the Transition Iteration:
The budget for this iteration is $20,000. WebNewsOnLine has secured this
funding.
All use cases have been implemented.
The primary goal of this iteration is to hand the system off to WebNewsOnLine
staff. Success will be measured by final user acceptance and operations
acceptance.